Juniper commissions 145.99 MWp Chapalgaon solar project in Maharashtra
Juniper Green Energy is proud to announce the early commissioning of 145.99 MWp / 100 MW of its solar power project in Chapalgaon, Maharashtra, which will supply power to MSEDCL. The plant was commissioned on May 22, 2025, an impressive 19 months ahead of the Scheduled Commercial Operation Date, and within 2.5 months of PPA signing on March 7, 2025. The project will operate at a full capacity of 145.99 MWp from its commissioning.
3 days ago2 min read